- Rate analysis of concrete used of reference book IS Code 1200 part 2 (IS Code 1200 part 2 used for measurement), IS Code 2212, and CPWD Part 1.
- All calculations of concrete for rate analysis. This calculation calculates of cement, sand, concrete (Concrete = Cement + Sand + aggregate mixture this call concrete) for materials.
- Concrete is used a sum different proportions 1:0.5:1, 1:1:2, 1:1.5:3, 1:2:4, 1:3:6 etc.(1 cement: 5 Sand: 10 Aggregate). This quantity estimation of concrete is required for the rate analysis.
Important Point in Rate Analysis of Concrete
Important Point
Rate Analysis for Concrete
- Quantity of material and Its cost.
- Labour cost.
- Cost of equipment or Tools and plants( 1.5%)
- Water charges (1.5%)
- Overhead expenses (2 to 5%)
- Contractor profit (10%)
Rate Analysis for Cement Mortar
Labours for 1m³ | No’s | Amount |
Mazdoor | 0.75 | Rs. 375 |
Bhisti | 0.07 | Rs. 28 |
Rs. 403 |
Concrete Rate Analysis
For concrete rate analysis, we need first to organize the data we need for calculations. This includes materials, steel, craft, shuttering charge, and water charge.
Suggested Read –
- What Is Leveling | Leveling Methods
- What is Bitumen And Bitumens Types
- What Is Honeycomb In Concrete | Cause | Cure | Type of Grouting
- What is Rate Analysis | Rate Analysis of Earth Work, Brick, Concrete and Plaster
- How to Use Rate Analysis of Brick Work Calculator| Rate Analysis of Brick Work Calculator